Working example / Project finance

EPC milestone cash flow calculator

Equipment can be on site and the supplier paid before the client accepts the work. Move the acceptance date to see which month the milestone cash lands in and how much cash the project needs in between.

Separate the delivery from the money.

This illustrative engineering, procurement and construction (EPC) package starts with $20,000. Equipment arrives on 22 January 2027. The supplier is paid $48,000 on 29 January under a separate payment schedule. Neither the delivery nor the client’s sign-off moves that payment.

The contract in this example allows a $72,000 progress invoice after acceptance. Accounts plans to issue it two calendar days after sign-off; the client is assumed to pay 30 calendar days from invoice issue, not from delivery. A separate $12,000 site crew payment falls on 10 March.

Try the delay: Acceptance on 26 January puts the receipt on 27 February. Move acceptance to 26 February: the invoice moves to 28 February and the receipt to 30 March. The crew now needs paying before the receipt, taking the cash shortfall from $28,000 to $40,000.

Edit the sample payment schedule.

Use positive amounts in NZD. Only the supplier payment, crew payment and client receipt move cash. These are scenario dates, not a forecast or instructions to issue an invoice. All offsets count calendar days without weekend or holiday adjustments; there is no tax, retention, financing or other project cash in the example.

Download the editable milestone cash flow template (Excel). The workbook includes the sample inputs and formulas. No sign-up needed.

Read the cash gap, not just the month-end balance.

Lowest daily balance: −$28,000 on 29 Jan 2027. Cash needed to stay at or above zero: $28,000.

Week ending 28 Feb 2027: closing cash $44,000. With acceptance delayed to 26 Feb, that same week closes at −$28,000 instead.

Equipment delivered
22 Jan 2027
Supplier paid
29 Jan 2027
Milestone accepted
26 Jan 2027
Planned invoice issue
28 Jan 2027
Expected client receipt
27 Feb 2027
Crew paid
10 Mar 2027
Monthly cash movements · NZD
MonthOpeningReceiptsPaymentsLowest balanceClosing
Jan 2027$20,000$0$48,000−$28,000−$28,000
Feb 2027−$28,000$72,000$0−$28,000$44,000
Mar 2027$44,000$0$12,000$32,000$32,000

Closing cash = opening cash + receipts − payments. The lowest balance includes opening cash and each day’s closing balance, with same-day flows netted. A negative low is the amount unfunded that day, even if month-end cash is positive.